Sign up for updates           |            Sign up for updates           |            Sign up for updates           |            Sign up for updates           |            Sign up for updates           |            Sign up for updates           |            Sign up for updates           |            Sign up for updates           |            Sign up for updates           |            Sign up for updates           |            Sign up for updates           |            Sign up for updates           |            Sign up for updates           |            Sign up for updates           |           

Geothermal

No.ProjectLocationDescriptionProject OwnerDate StartStatusTarget CompletionSource
1Lumut Balai Unit 2Muara Enim Regency, South SumatraA 55 MW geothermal generating unit in the Lumut Balai Geothermal Working Area (WKP), adding electricity to the PLN grid.PT Pertamina Geothermal Energy Tbk (PGE), a Pertamina subsidiary; Pertamina is an Indonesian SOE.First synchronization: 14 June 2025Operational. Initial synchronization was completed in June 2025; the unit subsequently reached commercial operation in June 2025.COD achieved: 30 June 2025PGE
2Lumut Balai Unit 3Lumut Balai WKP, South SumatraA 55 MW expansion of PGE’s Lumut Balai geothermal cluster, intended to increase low-emission electricity supply.PGE / PT Pertamina (Persero).Formal development kick-off: 12 January 2026Under development / construction initiated. PGE formally launched the project via a kick-off meeting.2030PGE
3Lumut Balai Unit 4Lumut Balai WKP, South SumatraA planned 55 MW follow-on expansion within the Lumut Balai geothermal development cluster.PGE / PT Pertamina (Persero).Public project inclusion in Bappenas Blue Book: 2025Preparation / financing-development stage.2032PGE
4Lahendong Units 7–8Lahendong WKP, North SulawesiA 50 MW geothermal expansion consisting of Units 7–8 at the Lahendong field.PGE / PT Pertamina (Persero).Public financing-project announcement: 5 June 2026Development and financing stage. The project was named in Indonesia’s 2026 Green Book for prospective international financing.2030PGE
5Lahendong Bottoming Unit 1Lahendong, North SulawesiA 15 MW binary/cogeneration project designed to generate additional electricity from geothermal heat already available in existing operations.Consortium: PGE and PT PLN Indonesia Power (PLN IP); the collaboration was coordinated by PT Danantara Asset Management.Consortium Commitment Agreement / HoA: August 2025Early development / consortium stage. PGE and PLN IP concluded a consortium commitment agreement; project development remains subject to detailed implementation processes.PGE
6Ulubelu Bottoming UnitUlubelu WKP, LampungA 30 MW bottoming-unit/cogeneration geothermal project that captures additional energy from the existing Ulubelu geothermal system. It is a Danantara-facilitated “quick-win” project.Consortium: PGE and PLN IP; facilitated by PT Danantara Asset Management.HoA and consortium agreement: August 2025; tariff agreement with PLN: December 2025Pre-construction development. The consortium agreed the electricity tariff with PLN and planned joint-venture formation, EPCC procurement, and PPA acceleration.2027PGE
7Dieng Unit 2Dieng WKP, Wonosobo Regency, Central JavaA 55 MW geothermal power-plant expansion at the existing Dieng field, supplying the Java–Madura–Bali interconnected grid.PT Geo Dipa Energi (Persero), a geothermal SOE.Groundbreaking: 25 June 2026Under construction. Geo Dipa had previously completed well testing; it then began physical construction in June 2026.March 2028ADB
8Patuha Unit 2Patuha WKP, Pasirjambu, Bandung Regency, West JavaA 55 MW expansion at the existing Patuha geothermal field, intended to double the field’s installed geothermal generation from its existing 55 MW unit.PT Geo Dipa Energi (Persero), a geothermal SOE.Development drilling and well testing were completed by 2024–2025; EPC development began in 2025.Under construction. Reported construction progress was about 35%; peak construction was expected in Q4 2026.May 2027ADB
9Gunung Tiga / Ulubelu Extension IUlubelu geothermal area, LampungA proposed PGE geothermal expansion project included in Indonesia’s national development-project pipeline. Public releases describe it as part of PGE’s broader geothermal growth program but do not provide a unit-level MW figure or standalone COD date.PGE / PT Pertamina (Persero).Entered Bappenas’ 2025–2029 Blue Book: 2025Preparation / project-development and potential concessional-finance stage.Expected within the aggregate rollout period of 2029–2032; no standalone COD disclosed.PGE
10Dieng and Patuha Expansion ProgrammeCentral Java and West JavaThe ADB-backed umbrella programme supporting the commissioning of additional geothermal capacity at Dieng and Patuha; ADB describes the programme as adding 110 MW in total, split into 55 MW at each field.PT Geo Dipa Energi (Persero); supported by the Asian Development Bank.ADB project approval / support framework publicly reported in 2025Active implementation. It encompasses the Dieng Unit 2 and Patuha Unit 2 projects.The underlying projects have separate targets: Patuha Unit 2 in 2027 and Dieng Unit 2 in 2028.ADB

Location

Lumut Balai Unit 2
A 55 MW geothermal generating unit in the Lumut Balai Geothermal Working Area (WKP), adding electricity to the PLN grid.
Muara Enim Regency, South Sumatra
Lumut Balai Unit 3
A 55 MW expansion of PGE’s Lumut Balai geothermal cluster, intended to increase low-emission electricity supply.
Lumut Balai WKP, South Sumatra
Lumut Balai Unit 4
A planned 55 MW follow-on expansion within the Lumut Balai geothermal development cluster.
Lumut Balai WKP, South Sumatra
Lahendong Units 7–8
A 50 MW geothermal expansion consisting of Units 7–8 at the Lahendong field.
Lahendong WKP, North Sulawesi
Lahendong Bottoming Unit 1
A 15 MW binary/cogeneration project designed to generate additional electricity from geothermal heat already available in existing operations.
Lahendong, North Sulawesi
Ulubelu Bottoming Unit
A 30 MW bottoming-unit/cogeneration geothermal project that captures additional energy from the existing Ulubelu geothermal system. It is a Danantara-facilitated “quick-win” project.
Ulubelu WKP, Lampung
Dieng Unit 2
A 55 MW geothermal power-plant expansion at the existing Dieng field, supplying the Java–Madura–Bali interconnected grid.
Dieng WKP, Wonosobo Regency, Central Java
Patuha Unit 2
A 55 MW expansion at the existing Patuha geothermal field, intended to double the field’s installed geothermal generation from its existing 55 MW unit.
Patuha WKP, Pasirjambu, Bandung Regency, West Java
Gunung Tiga / Ulubelu Extension I
A proposed PGE geothermal expansion project included in Indonesia’s national development-project pipeline. Public releases describe it as part of PGE’s broader geothermal growth program but do not provide a unit-level MW figure or standalone COD date.
Ulubelu geothermal area, Lampung
Dieng and Patuha Expansion Programme
The ADB-backed umbrella programme supporting the commissioning of additional geothermal capacity at Dieng and Patuha; ADB describes the programme as adding 110 MW in total, split into 55 MW at each field.
Dieng WKP, Wonosobo Regency, Central Java
Dieng and Patuha Expansion Programme
The ADB-backed umbrella programme supporting the commissioning of additional geothermal capacity at Dieng and Patuha; ADB describes the programme as adding 110 MW in total, split into 55 MW at each field.
Patuha WKP, Pasirjambu, Bandung Regency, West Java