Sign up for updates           |            Sign up for updates           |            Sign up for updates           |            Sign up for updates           |            Sign up for updates           |            Sign up for updates           |            Sign up for updates           |            Sign up for updates           |            Sign up for updates           |            Sign up for updates           |            Sign up for updates           |            Sign up for updates           |            Sign up for updates           |            Sign up for updates           |           

Waste-To-Energy

No.ProjectLocationDescriptionProject OwnerDate StartStatusTarget CompletionSource
1PLTSa BenowoSurabaya, East JavaWaste-to-energy facilities at Benowo landfill. The project includes landfill-gas power generation and a thermal gasification-based plant; total reported capacity is around 10.65 MW (1.65 MW landfill gas plus 9 MW gasification).Surabaya City Government owns/controls the landfill asset. PT Sumber Organik is the independent power producer/operator under a 20-year landfill-management concession; PLN is the power offtaker.PT Sumber Organik’s concession began in October 2012; landfill-gas generation began November 2015.Operating. Landfill-gas facility has operated since November 2015; the 9 MW gasification facility was inaugurated in May 2021.Already operating. PLN stated its cooperation with PT Sumber Organik runs through 2032.PLN
2PLTSa Putri CempoSurakarta, Central JavaWaste-to-energy plant at Putri Cempo final disposal site. Reported design: processing about 545 tonnes/day of waste and producing 8 MW, of which 5 MW is supplied to PLN.Public partner: Surakarta City Government. Project operator/developer: PT Solo Citra Metro Plasma Power (SCMPP).Project development dates vary by source; the municipal cooperation framework predates commissioning. The operational project reached COD/operation in October 2023.Operating. The city government confirms formal operation since October 2023. However, separate reporting in 2025 indicated actual waste throughput was still materially below the 545-tonne/day design capacity.Commercial operation commenced 30 October 2023. Earlier municipal planning had targeted COD for December 2022, which was delayed.The Surakarta City Government
3PSEL Denpasar RayaPedungan, South Denpasar, BaliA moving-grate waste-to-energy plant for Greater Denpasar, intended to process municipal waste and generate electricity.National project sponsors: PT Danantara Investment Management (DIM) and PT Daya Energi Bersih Nusantara (Denera). Project Development and Operating Company/BUPP: Nusantara Bali New Energy; the selected international operator/developer is Zhejiang Weiming Environment Protection.8 July 2026Construction launched / implementation stage. This was the first Danantara PSEL location to hold an inauguration/groundbreaking.First half of 2028 is the official target commercial operation date.Danantara Indonesia
4PSEL Kota BekasiBekasi City, West JavaWaste-to-energy project intended to process up to 1,500 tonnes of municipal waste per day into electricity.DIM and Denera lead the investment programme. The selected consortium is Wangneng Adyawinsa Energi Consortium, led by Wangneng Environment; the project SPV/BUPP has been reported as PT Wangneng Bekasi Environment Nusantara.26 August 2026Construction started. It is one of the initial Danantara WtE projects and has national strategic-project status.Reported target: mid-2028.CNINFO
5PSEL Bogor RayaGreater Bogor, West JavaRegional waste-to-energy project for Bogor-area municipal waste. Earlier public descriptions indicate a planned capacity of approximately 1,500 tonnes/day.DIM and Denera are national programme sponsors. Selected developer/operator: Zhejiang Weiming Environment Protection. Project company reported as PT Weiming Nusantara Bogor New Energy.Partner selection announced 13 March 2026; regional project cooperation was reported in April 2026. Recent news report said ground breaking to be held in September 17, 2026.Pre-construction / project implementation preparation. Partner selection and intergovernmental cooperation have been announced; an independently verified construction start date was not available in the reviewed official material.No official, project-specific COD target was located in the reviewed sources. Treat prior references to 2027 start-up as indicative only, pending financing and construction confirmation.Antaranews
6PSEL / PLTSa Legok NangkaBandung Regency, West JavaRegional waste-to-energy project serving six areas: Bandung City, Bandung Regency, West Bandung, Cimahi, Sumedang, and Garut. Planned capacity: 40.79 MW, with roughly 2,000 tonnes/day of waste processing.Provincial public sponsor: West Java Provincial Government. Implementing project company: PT Jabar Environmental Solutions (JES). Earlier project documentation identifies a Sumitomo–Hitachi Zosen consortium as technology/development partner. PLN is the electricity offtaker.29 July 2026Under construction. Groundbreaking occurred in July 2026; PLN had signed a power-purchase agreement with JES in March 2026.End-2029 target operation; reported construction duration is about 41 months.Detik
7PSEL Medan RayaNorth SumatraBatch-II regional waste-to-energy project under Danantara’s national PSEL programme.Programme sponsors: DIM and Denera. Selected partner: Nusantara Energi Hijau Consortium / BGE Sentosa Utama.Selected partner announced 13 July 2026; CLoA awarded 21 July 2026.Conditional Letter of Award (CLoA); feasibility study and project preparation. Not yet at financial close or construction based on available sources.No project-specific COD disclosed. Batch-II groundbreaking target: December 2026–January 2027.Danantara Indonesia
8PSEL Kabupaten BekasiWest JavaA separate Batch-II project for Bekasi Regency; it should not be conflated with the City of Bekasi/Bantar Gebang project.DIM and Denera. Selected partner: Everbright Cemerlang Energy Consortium / Everbright Harmoni.Selected partner announced 13 July 2026; CLoA awarded 21 July 2026.CLoA; feasibility-study and pre-construction preparation.No project-specific COD disclosed. Batch-II groundbreaking target: December 2026–January 2027.Danantara Indonesia
9PSEL Lampung RayaLampungBatch-II regional waste-to-energy project.DIM and Denera. Selected partner: Bumi Biru Indonesia Consortium, involving SUS Indonesia Holding and PT Indoplas Dewata Energi.Selected partner announced 13 July 2026; CLoA awarded 21 July 2026.CLoA; feasibility-study and pre-construction preparation.No project-specific COD disclosed. Batch-II groundbreaking target: December 2026–January 2027.Danantara Indonesia
10PSEL Serang RayaBantenBatch-II regional waste-to-energy project.DIM and Denera. Selected partner: Masa Depan Energi Indonesia Consortium, reported to involve Chandra Waste Energy and BGE.Selected partner announced 13 July 2026; CLoA awarded 21 July 2026.CLoA; feasibility-study and pre-construction preparation.No project-specific COD disclosed. Batch-II groundbreaking target: December 2026–January 2027.Danantara Indonesia
11PSEL Semarang RayaCentral JavaNew Batch-II regional WtE project. It is distinct from the earlier Jatibarang landfill-gas/PLTSa arrangement, whose operating period has ended.DIM and Denera. Selected partner: Veolia Environmental Services Asia Pte. Ltd.Selected partner announced 13 July 2026; CLoA awarded 21 July 2026.CLoA; feasibility-study and pre-construction preparation.No project-specific COD disclosed. Batch-II groundbreaking target: December 2026–January 2027.Danantara Indonesia
12PSEL Surabaya RayaEast JavaBatch-II regional PSEL project, separate from operational PLTSa Benowo.DIM and Denera. Selected partner: Mentari Citra Lestari Consortium, reported to include Bakrie Power and SUS Indonesia.Selected partner announced 13 July 2026; CLoA awarded 21 July 2026.CLoA; feasibility-study and pre-construction preparation.No project-specific COD disclosed. Batch-II groundbreaking target: December 2026–January 2027.Danantara Indonesia
13PSEL Bogor Raya 2West JavaA second, separately procured Bogor-area project in Batch II; distinct from the initial Bogor Raya project awarded to Weiming.DIM and Denera. Selected partner: MPM–CEVIA Consortium / Mega Power CEVIA.Selected partner announced 13 July 2026; CLoA awarded 21 July 2026.CLoA; feasibility-study and pre-construction preparation.No project-specific COD disclosed. Batch-II groundbreaking target: December 2026–January 2027.Danantara Indonesia
14PSEL Yogyakarta RayaSpecial Region of YogyakartaRegional WtE project serving the Yogyakarta urban area and participating local governments, including Yogyakarta City, Bantul, and Sleman.DIM and Denera. Selected partner: Cakra Energi Lestari Consortium, reported to involve Pertamina Power Indonesia, Tianjin TEDA Environmental Protection, and CITICC International Investment.Selected partner announced 13 July 2026; CLoA awarded 21 July 2026.Pre-construction. Partner has received CLoA; Danantara later indicated that groundbreaking was targeted for December 2026.Groundbreaking targeted for December 2026. No public project-specific COD date was located.Antaranews

Location

PLTSa Benowo
Waste-to-energy facilities at Benowo landfill. The project includes landfill-gas power generation and a thermal gasification-based plant; total reported capacity is around 10.65 MW (1.65 MW landfill gas plus 9 MW gasification).
Surabaya, East Java
PLTSa Putri Cempo
Waste-to-energy plant at Putri Cempo final disposal site. Reported design: processing about 545 tonnes/day of waste and producing 8 MW, of which 5 MW is supplied to PLN.
Surakarta, Central Java
PSEL Denpasar Raya
A moving-grate waste-to-energy plant for Greater Denpasar, intended to process municipal waste and generate electricity.
Pedungan, South Denpasar, Bali
PSEL Kota Bekasi
Waste-to-energy project intended to process up to 1,500 tonnes of municipal waste per day into electricity.
Bekasi City, West Java
PSEL Bogor Raya
Regional waste-to-energy project for Bogor-area municipal waste. Earlier public descriptions indicate a planned capacity of approximately 1,500 tonnes/day.
Greater Bogor, West Java
PSEL / PLTSa Legok Nangka
Regional waste-to-energy project serving six areas: Bandung City, Bandung Regency, West Bandung, Cimahi, Sumedang, and Garut. Planned capacity: 40.79 MW, with roughly 2,000 tonnes/day of waste processing.
Bandung Regency, West Java
PSEL Medan Raya
Batch-II regional waste-to-energy project under Danantara’s national PSEL programme.
North Sumatra
PSEL Kabupaten Bekasi
A separate Batch-II project for Bekasi Regency; it should not be conflated with the City of Bekasi/Bantar Gebang project.
West Java
PSEL Lampung Raya
Batch-II regional waste-to-energy project.
Lampung
PSEL Serang Raya
Batch-II regional waste-to-energy project.
Banten
PSEL Semarang Raya
New Batch-II regional WtE project. It is distinct from the earlier Jatibarang landfill-gas/PLTSa arrangement, whose operating period has ended.
Central Java
PSEL Surabaya Raya
Batch-II regional PSEL project, separate from operational PLTSa Benowo.
East Java
PSEL Bogor Raya 2
A second, separately procured Bogor-area project in Batch II; distinct from the initial Bogor Raya project awarded to Weiming.
West Java
PSEL Yogyakarta Raya
Regional WtE project serving the Yogyakarta urban area and participating local governments, including Yogyakarta City, Bantul, and Sleman.
Special Region of Yogyakarta